序号 |
标段名称 |
专项资格要求 |
|
全厂压型钢板
Profiled Steel Sheets |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
厂用电智能抄表系统
Reading System of Unit Auxiliary Power Meter |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
发变组故障录波器
Fault Recorder |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have 1 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
同期装置屏(含励磁涌流装置屏)
Generator Automatic Synchronized System |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
测温元件及附件
Temperature Element and Accessories |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
发变组和停机检修变保护
Generator-transformer Unit Protection |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
全厂工业电视闭路监视系统
CCTV |
投标人须在近5年内,至少有1个600MW及以上燃煤发电机组全厂工业闭路电视系统的集成业绩,且商业运行2年及以上。
The bidder shall have at least a integrated performances of the industrial closed-circuit television system of the coal-fired generating units of 600MW and above in the past five years, and the commercial operation shall be for 2 years and above . |
|
化学实验室分析仪器和台柜
Chemical Laboratory Analytical Instruments and Counters |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
变送器及电度表屏
Unit Transmitter and Meter Panel |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
汽机房辅助容器
Auxiliary Vessels of Turbine House |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
氢气供应系统
Hydrogen Supply System |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩。
Bidders must have a 600MW and above coal-fired generating units projects in the past five years, and the performance of commercial operations for two years and above. |
|
消防泵房设备
Fire Fighting Pumps House |
投标人必须已获得FM和UL认证证书,并保证本项目所提供的所有产品取得FM和UL认证;同时,投标人必须有国外项目提供FM和UL认证产品的供货业绩。
Bidders must be qualified for FM and UL certification, and ensure that all products provided in this project are qualified for FM and UL certification. And bidders must have the performance of supplying FM and UL certificated products for abroad project. |
|
含氨废水处理系统
Ammonia Wastewater Processing System |
投标人须在5年内至少有1个600MW及以上超超临界火电项目工业废水处理系统2年及以上商业运行的业绩。
The Tenderer shall in 5 years have the reference of 2 years’ commercial operation of industrial wastewater processing system in a 2 super-critical thermal power plant projects with the capacity of 600MW and above. |
|
工业废水处理系统
Industrial Wastewater processing system |
投标人须在5年内至少有1个含氨废水处理系统(采用厌氧氨氧化+A/O工艺,处理含氨废水项目)2年及以上商业运行的业绩。
The Tenderere shall in 5 years have the reference of 2 years’s commercial operation of 1 set the ammonia wastewater processing system (Anammox +A/O process is adopted to treat ammonia wastewater) |
|
全厂检修起吊设备
Lifting Equipment |
投标人须在近5年内有1个600MW及以上燃煤发电机组项目,2年及以上商业运行的业绩,每个项目的起重设备合同订单不少于20台,投标人必须具有海外业绩。
The Tenderer shall have a 600MW and above coal-fired power plant projects in the past five years, the performance of commercial operation of 2 years and above, and no less than 20 contracting orders for lifting equipment per project. Bidder must have overseas performance |